Pass E_ACTCLD_21 Exam in First Attempt Guaranteed 2021 Dumps!
E_ACTCLD_21 Dumps Full Questions - Exam Study Guide
NEW QUESTION 54
What is the minimum number of quality gates mandated by the SAP Activate methodology?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 55
How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 answers to this question.
- A. Demo the SAP model company
- B. Solution review for waves
- C. User acceptance test
Answer: B,C
NEW QUESTION 56
What does the side-by-side extensibility option mean?
- A. Transfer reporting to BW/4HANA
- B. Extensibility based on the SAP cloud platform and published APIs
- C. Context-aware SAP S/4HANA extensions, focused on tight integration
- D. Have two SAP S/4HANA instances-one for standard code, and another for customer developments
Answer: B
NEW QUESTION 57
The hypercare period is part of which phase?
- A. Explore
- B. Go-Live
- C. Realize
- D. Deploy
Answer: D
NEW QUESTION 58
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
- A. Go-Live scope is fixed on the first of January the following year.
- B. Project scope and planning are completed and final.
- C. User Stories are in Ready state for only the first 2 to 3 sprints.
- D. Timelines of the sprint may differ due to the workload.
Answer: C
NEW QUESTION 59
Which of the following statements about Scrum is? Please choose the answer.
- A. In Scrum, the team is Self-organized, define all task necessary for all project life cycle.
- B. Scrum Master defines and prioritizes features and gathers requirements.
- C. In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
- D. The three ceremonies are sprint planning, daily scrum, sprint review (retrospective).
Answer: D
NEW QUESTION 60
What is the purpose of the scrum board?
- A. To manage the resource load
- B. To document the results of the integration test
- C. To show the functional breakdown of the solution scope
- D. To visualize team progress
Answer: D
NEW QUESTION 61
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 answers to this question.
- A. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option
- B. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
- C. There are different roles in the application design and configuration workstream
- D. Different sets of workstreams are used for these transition paths
Answer: A,B
NEW QUESTION 62
What are some of the key characteristics of the implementation approach in the SAP Activate methodology? Note: There are 2 correct Answers to this question.
- A. Fixed scope
- B. Cloud ready
- C. Based on ready-to-use content
- D. On premise only
Answer: B,C
NEW QUESTION 63
Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase?
There are 2 answers to this question.
- A. Kick-off workshop
- B. Configuration definition
- C. Integration prerequisites confirmation
- D. Fit-to-standard workshop
Answer: B,D
NEW QUESTION 64
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: A
NEW QUESTION 65
What do you do during post cutover?
- A. Perform the Verification Session of the SAP Going Live Check
- B. Setup Operational Support
- C. Perform Technical System Test
- D. Conduct Organizational Readiness Check
Answer: A
NEW QUESTION 66
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.
What is the sequence of selected key deliverables across the project phases? Please choose the answer.
- A. 3rd option
a. Detailed system Assessment
b. Code Adjustment
c. Validation of Migration
d. Production Readiness Check - B. 4th option
a. Detailed system Assessment
b. Production Readiness Check
c. Code Adjustment
d. Validation of Migration - C. 1st option
a. Code adjustment
b. Detailed System Assessment
c. Production Readiness Check
d. Validation of Migration - D. 2nd option
a. Production Readiness Check
b. Detailed system Assessment
c. Code Adjustment
d. Validation of Migration
Answer: A
NEW QUESTION 67
What information does the project team need before they can correctly estimate the relative size of backlog user stories?
- A. Definition of Done
- B. Test strategy
- C. Available project resources
- D. Overall project schedule
Answer: A
NEW QUESTION 68
You are defining the testing strategy for your project. What would you include in a Scope of Integration test?
- A. The functionality of end-to-end business processes
- B. The connectivity between database and application servers
- C. The network communication
- D. The functionality of modular processes
Answer: A
NEW QUESTION 69
What solution operations framework can customers use to create a joint business and IT organization?
- A. Business Transformation Management Methodology
- B. SAP Activate
- C. Customer Center of Expertise
- D. SAP Roadmap Explorer
Answer: D
NEW QUESTION 70
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the answer.
- A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
- B. Relative estimate in ideal person days that reflects the best estimate provided by the project team
- C. Product Owner's relative estimate of the effort that will be needed to implement the user story
- D. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
Answer: C
NEW QUESTION 71
What is the most granular level of the methodology you can view in the SAP roadmap viewer?
- A. Deliverables
- B. Task
- C. Scenario
- D. Phase
Answer: B
NEW QUESTION 72
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation? Please choose the correct answer.
- A. Deliverable
- B. Task
- C. Scenario
- D. Scope Item
Answer: A
NEW QUESTION 73
What solution? Please choose the answer.
- A. SAP Implementation Guide
- B. Configuration Composer
- C. ABAP Workbench
- D. Expert Configuration
Answer: A
NEW QUESTION 74
Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct Answers to this question.
- A. Project Plan
- B. Change Management Roadmap
- C. End User Learning Needs Analysis
- D. Detailed Design - Business Process
- E. Learning Content
Answer: B,C,E
NEW QUESTION 75
What are the enablement areas relevant for all Customer Team members coming from the Business?
- A. Technical expertise
- B. Project management
- C. Solution expertise
- D. Workstream enablement
Answer: A,B,C
NEW QUESTION 76
......