NEW QUESTION 54
What is the minimum number of quality gates mandated by the SAP Activate methodology?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C

 

NEW QUESTION 55
How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 answers to this question.

  • A. Demo the SAP model company
  • B. Solution review for waves
  • C. User acceptance test

Answer: B,C

 

NEW QUESTION 56
What does the side-by-side extensibility option mean?

  • A. Transfer reporting to BW/4HANA
  • B. Extensibility based on the SAP cloud platform and published APIs
  • C. Context-aware SAP S/4HANA extensions, focused on tight integration
  • D. Have two SAP S/4HANA instances-one for standard code, and another for customer developments

Answer: B

 

NEW QUESTION 57
The hypercare period is part of which phase?

  • A. Explore
  • B. Go-Live
  • C. Realize
  • D. Deploy

Answer: D

 

NEW QUESTION 58
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?

  • A. Go-Live scope is fixed on the first of January the following year.
  • B. Project scope and planning are completed and final.
  • C. User Stories are in Ready state for only the first 2 to 3 sprints.
  • D. Timelines of the sprint may differ due to the workload.

Answer: C

 

NEW QUESTION 59
Which of the following statements about Scrum is? Please choose the answer.

  • A. In Scrum, the team is Self-organized, define all task necessary for all project life cycle.
  • B. Scrum Master defines and prioritizes features and gathers requirements.
  • C. In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
  • D. The three ceremonies are sprint planning, daily scrum, sprint review (retrospective).

Answer: D

 

NEW QUESTION 60
What is the purpose of the scrum board?

  • A. To manage the resource load
  • B. To document the results of the integration test
  • C. To show the functional breakdown of the solution scope
  • D. To visualize team progress

Answer: D

 

NEW QUESTION 61
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 answers to this question.

  • A. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option
  • B. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
  • C. There are different roles in the application design and configuration workstream
  • D. Different sets of workstreams are used for these transition paths

Answer: A,B

 

NEW QUESTION 62
What are some of the key characteristics of the implementation approach in the SAP Activate methodology? Note: There are 2 correct Answers to this question.

  • A. Fixed scope
  • B. Cloud ready
  • C. Based on ready-to-use content
  • D. On premise only

Answer: B,C

 

NEW QUESTION 63
Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase?
There are 2 answers to this question.

  • A. Kick-off workshop
  • B. Configuration definition
  • C. Integration prerequisites confirmation
  • D. Fit-to-standard workshop

Answer: B,D

 

NEW QUESTION 64
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: A

 

NEW QUESTION 65
What do you do during post cutover?

  • A. Perform the Verification Session of the SAP Going Live Check
  • B. Setup Operational Support
  • C. Perform Technical System Test
  • D. Conduct Organizational Readiness Check

Answer: A

 

NEW QUESTION 66
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.
What is the sequence of selected key deliverables across the project phases? Please choose the answer.

  • A. 3rd option
    a. Detailed system Assessment
    b. Code Adjustment
    c. Validation of Migration
    d. Production Readiness Check
  • B. 4th option
    a. Detailed system Assessment
    b. Production Readiness Check
    c. Code Adjustment
    d. Validation of Migration
  • C. 1st option
    a. Code adjustment
    b. Detailed System Assessment
    c. Production Readiness Check
    d. Validation of Migration
  • D. 2nd option
    a. Production Readiness Check
    b. Detailed system Assessment
    c. Code Adjustment
    d. Validation of Migration

Answer: A

 

NEW QUESTION 67
What information does the project team need before they can correctly estimate the relative size of backlog user stories?

  • A. Definition of Done
  • B. Test strategy
  • C. Available project resources
  • D. Overall project schedule

Answer: A

 

NEW QUESTION 68
You are defining the testing strategy for your project. What would you include in a Scope of Integration test?

  • A. The functionality of end-to-end business processes
  • B. The connectivity between database and application servers
  • C. The network communication
  • D. The functionality of modular processes

Answer: A

 

NEW QUESTION 69
What solution operations framework can customers use to create a joint business and IT organization?

  • A. Business Transformation Management Methodology
  • B. SAP Activate
  • C. Customer Center of Expertise
  • D. SAP Roadmap Explorer

Answer: D

 

NEW QUESTION 70
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the answer.

  • A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
  • B. Relative estimate in ideal person days that reflects the best estimate provided by the project team
  • C. Product Owner's relative estimate of the effort that will be needed to implement the user story
  • D. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks

Answer: C

 

NEW QUESTION 71
What is the most granular level of the methodology you can view in the SAP roadmap viewer?

  • A. Deliverables
  • B. Task
  • C. Scenario
  • D. Phase

Answer: B

 

NEW QUESTION 72
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation? Please choose the correct answer.

  • A. Deliverable
  • B. Task
  • C. Scenario
  • D. Scope Item

Answer: A

 

NEW QUESTION 73
What solution? Please choose the answer.

  • A. SAP Implementation Guide
  • B. Configuration Composer
  • C. ABAP Workbench
  • D. Expert Configuration

Answer: A

 

NEW QUESTION 74
Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct Answers to this question.

  • A. Project Plan
  • B. Change Management Roadmap
  • C. End User Learning Needs Analysis
  • D. Detailed Design - Business Process
  • E. Learning Content

Answer: B,C,E

 

NEW QUESTION 75
What are the enablement areas relevant for all Customer Team members coming from the Business?

  • A. Technical expertise
  • B. Project management
  • C. Solution expertise
  • D. Workstream enablement

Answer: A,B,C

 

NEW QUESTION 76
......