Most UptoDate SAP E_ACTCLD_21 Exam Dumps PDF 2022 [Q11-Q29]

Share

Most UptoDate SAP E_ACTCLD_21 Exam Dumps PDF 2022

100% Free SAP Certified Specialist E_ACTCLD_21 Dumps PDF Demo Cert Guide Cover


SAP E_ACTCLD_21 Exam Description:

The "SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager" certification exam verifies that the candidate has the knowledge required in the area of SAP project management. This exam validates whether SAP Cloud-focused project managers have advanced business skills and the ability to apply methodologies and tools. Aside from advanced communication and presentation skills, this certificate also verifies that the project manager has skills to manage internal and external stakeholders, basic knowledge of change management processes, and communicating these processes to others. This exam validates that project manager can successfully manage the end-to-end transition of the project from Sales to Realization, can develop roadmaps for project execution, and understand testing and quality management. In particular for SAP Cloud-related projects, the exam verifies that the Project Manager can apply the SAP Activate Methodology.


SAP E_ACTCLD_21 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Describe how the project team prepares release and sprint plans
  • Agile Project Delivery
Topic 2
  • Describe concepts, landscape overview and specifics in Workstreams
  • Agile Project Planning
Topic 3
  • Describe concepts, artefact flows, accelerators, tools and roles
  • Discuss key techniques used in agile projects
Topic 4
  • Provide an overview of content, tools and methodology elements
  • SAP Activate Elements


E_ACTCLD_21 Exam Certification Details:

Sample Questions: SAP E_ACTCLD_21 Exam Sample Question
Cut Score:65%
Exam:40 questions
Level:Associate
Languages:English

 

NEW QUESTION 11
Which of the following can be used to navigate through the roadmap? There are 2 answers to this question.

  • A. Tasks
  • B. Phases
  • C. Workstreams
  • D. Deliverables

Answer: B,C

 

NEW QUESTION 12
Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?

  • A. Detailed bottom-up effort estimate that breaks each User Story up into hours or shorter tasks
  • B. Relative estimate in Ideal Person Days that reflects the best estimate provided by the project team
  • C. Product owner's relative estimate of the effort that will be needed to implement the User Story
  • D. Detailed bottom-up effort estimate by the Scrum Master in story points based on the User Story complexity

Answer: B

 

NEW QUESTION 13
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 answers to this question.

  • A. Blu-ray disks
  • B. SAP Solution Builder tool
  • C. SAP cloud appliance library
  • D. SAP App centre

Answer: A,C

 

NEW QUESTION 14
What can you see in the process content viewer?

  • A. Business process models
  • B. SAP Activate tasks
  • C. Business user roles
  • D. Business process value flows

Answer: D

 

NEW QUESTION 15
Selective Data Transition covers the migration of relevant business data from SAP ERP to SAP S/4HANA.
It allows a tailored scope between System Conversion and New Implementation with the flexibility to adapt data and processes in one transition step.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 16
What are some of the values of SAP Cloud ALM operations? 3 correct answers

  • A. it provides end-to-end transparency
  • B. it provides license management capabilities
  • C. it provides improved efficiency and automation
  • D. it provides a solution readiness check
  • E. it provides reduced cost of operations

Answer: A,C,E

 

NEW QUESTION 17
What do you do during Sprint Execution? Please choose the answer.

  • A. Measure the sprint progress with a percentage complete report
  • B. Present status of selected user stories in the sprint scope on a scrumboard
  • C. End a sprint when the sprint backlog items are all complete
  • D. Hold a retrospective at the end of each week

Answer: A

 

NEW QUESTION 18
Implementation of which solutions are supported by the SAP Activate Framework?

  • A. SAP S/4HANA On-Premise
  • B. SAP SuccessFactors
  • C. C4C
  • D. BW/4HANA On-Premise
  • E. SAP S/4HANA Cloud

Answer: A,B,C,D,E

 

NEW QUESTION 19
In SAP Activate, what tool is used in the during the Realize phase to make forecasts based on actual data?

  • A. Product Increment
  • B. Release Plan
  • C. Burndown Chart
  • D. Project Plan

Answer: C

 

NEW QUESTION 20
Which activity helps the project team to add the user stories to the product backlog? Please choose the answer.

  • A. Conducting the Solution Validation
  • B. Assessing Project Risks
  • C. Planning the User Acceptance Test
  • D. Preparing a Project Schedule

Answer: A

 

NEW QUESTION 21
In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the answer.

  • A. Leverages iterative incremental build
  • B. Includes Fit/Gap analysis instead of Blueprint
  • C. Supports only new implementations
  • D. Supports cloud deployments

Answer: B

 

NEW QUESTION 22
Where can you find data migration templates?

  • A. SAP Cloud Appliance Library
  • B. SAP S/4 HANA migration cockpit
  • C. SAP Best Practice Explorer
  • D. Roadmap Viewer

Answer: B

 

NEW QUESTION 23
Which criterion does the Product Owner use to sequence the product backlog? Please choose the answer.

  • A. Complexity
  • B. Business priority
  • C. Relative effort
  • D. Resource availability

Answer: B

 

NEW QUESTION 24
Which deliverable is specific to on-premise and NOT for the cloud? Please choose the answer.

  • A. Adaptation Specification
  • B. Learning Needs Analysis
  • C. Technical Design Solution
  • D. Knowledge Transfer

Answer: D

 

NEW QUESTION 25
What did the order processing agent Rafael find out with his root cause analysis? Note: There are 2 answers to this question.

  • A. Payments for sales items have been received from customer AB Logistics Ltd. in SAP S/4HANA Cloud, but they have not yet been cleared.
  • B. All sales order items with a credit block had been sold to the same customer.
  • C. Janet, the process manager, had recently been checking the "Sales Documents with Credit Block KPI".
  • D. A large number of sales order items recently created require urgent next-day delivery.

Answer: B,D

 

NEW QUESTION 26
Which tools does SAP Activate provide to support Guided Configuration? There are 3 answers to this question.

  • A. Solution Builder
  • B. Expert Configuration
  • C. SAP Solution Composer
  • D. Self Service Configuration
  • E. Model Company

Answer: A,B,D

 

NEW QUESTION 27
What is SAP Activate? Please choose the answer.

  • A. A step-by-step instruction on how to remove from SAP best practices to your custom solution
  • B. A bundle of ASAP, SAP Launch, and Rapid Deployment Solutions
  • C. A methodology for each of the deployment modes (cloud, on-premise, hybrid)
  • D. A combination of SAP best practices, methodology, and guided configuration

Answer: D

 

NEW QUESTION 28
What are the enablement areas relevant for all Customer Team members coming from the Business?

  • A. Project management
  • B. Solution expertise
  • C. Technical expertise
  • D. Workstream enablement

Answer: A,B,C

 

NEW QUESTION 29
......

Updated SAP E_ACTCLD_21 Dumps – PDF & Online Engine: https://www.actualtorrent.com/E_ACTCLD_21-questions-answers.html