[Mar-2023] Verified EXIN Exam Dumps with PR2F Exam Study Guide [Q57-Q73]

Share

[Mar-2023] Verified EXIN Exam Dumps with PR2F Exam Study Guide

Best Quality EXIN PR2F Exam Questions ActualTorrent Realistic Practice Exams [2023]


Topics of PRINCE2-Foundation: PRINCE2 Foundation Exam

PRINC2-Foundation exam certified professionals are in great demand nowadays. This exam has its own worth and this exam comprises different topics and these topics are necessary in order to prepare and pass the examination with good marks. The topics of the exam are:

  1. Recall
  2. Describe
  3. Explain the PRINCE2 principles
  4. Explain which aspect of the project to be tailored
  5. Business Case theme
  6. Organization theme
  7. Quality Theme
  8. Plans Theme
  9. Risk Theme
  10. Change Theme
  11. Progress Theme
  12. Explain the purpose of PRINCE2 processes
  13. Explain the brief objective of the processes
  14. Explain the context of the PRINCE2 processes

PRINCE2 Foundation PR2F Exam

PRINCE2 Foundation PR2F Exam which is related to Exin PRINCE2 Foundation and credits toward Exin Project Management Certification. This exam focuses on the characteristics and context of a project and the benefits of adopting PRINCE2 the purpose of the PRINCE2 roles management, products, and themes, objectives and context of the PRINCE2 to process. It also deals with the ability to provide a structured universally acceptable project management method that covers the PRINCE2 principles, themes and processes required to successfully deliver the projects within time, cost and quality constraints.

 

NEW QUESTION 57
Which is one of the six aspects of project performance that needs to be managed?

  • A. Progress
  • B. Security
  • C. Risk
  • D. Change

Answer: C

Explanation:
Section: Volume A
Explanation

 

NEW QUESTION 58
Which is a purpose of a Project Product Description?

  • A. Document the project mandate and gain approval for the project from the Project Board
  • B. Define the quality required of the project's product
  • C. Provide the initial project budget to be refined in the Business Case
  • D. Form part of the Work Package for the project product

Answer: B

 

NEW QUESTION 59
Which is a responsibility of the project board?

  • A. To ensure effective communication with external stakeholders
  • B. To implement the change control approach
  • C. To ensure production of the project's outputs
  • D. To manage the team managers and project support

Answer: A

 

NEW QUESTION 60
Which process covers the work done by external suppliers who may NOT be using
PRINCE2?

  • A. Closing a Project
  • B. Directing a Project
  • C. Managing a Stage Boundary
  • D. Managing Product Delivery

Answer: D

 

NEW QUESTION 61
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

  • A. Executive
  • B. Explanation:
    QUESTIONNO:222
    Which role is part of the Project Board?
    A. Corporate or programme management
    B. Risk owner
    C. Project Manager
    D. Senior Supplier
  • C. Project Assurance
  • D. Corporate group
  • E. Project Board

Answer: D

 

NEW QUESTION 62
Which is an objective of the 'directing a project' process?

  • A. To define how risks, issues and changes will be managed
  • B. To review and approve a project mandate
  • C. To ensure corporate or programme management has an interface to the project
  • D. To obtain approval for completed products

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Directing_a_Project#Objective

 

NEW QUESTION 63
Which is a purpose of a Risk Register?

  • A. Capture risks that may occur during the project
  • B. Record how risk management activities will be undertaken on the project
  • C. Capture issues which are impacting on the delivery of the project objectives
  • D. Record the risk tolerance for the project

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:

 

NEW QUESTION 64
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

  • A. In exception situations
  • B. When a change is raised
  • C. Throughout each stage
  • D. At the start of the project

Answer: C

Explanation:
Explanation
Reference https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/

 

NEW QUESTION 65
Which is NOT a recommended quality review team role?

  • A. Chair
  • B. Producer
  • C. Administrator
  • D. Reviewer

Answer: B

 

NEW QUESTION 66
Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

  • A. project approach appropriate for delivering a project is selected
  • B. Project Brief is assembled and approved
  • C. minimum necessary is done to decide if a project is worthwhile
  • D. aim is to establish sound foundations to achieve a successful project

Answer: D

 

NEW QUESTION 67
How are team managers involved in tailoring PRINCE2 suit the project?

  • A. Team managers may advice on tailoring to improve the management of work packages
  • B. Team managers should document the tailoring of the work packages
  • C. Team managers are accountable for the tailoring of the work packages
  • D. Team managers should not be involved in tailoring PRINCE2

Answer: A

 

NEW QUESTION 68
Which of the following statements about stakeholders are true?
1.Someone who thinks they will be affected by a project is a stakeholder on that project
2.Stakeholders may be internal or external to the corporate organization

  • A. Neither 1 or 2 are true
  • B. Both 1 and 2 are true
  • C. Only 1 is true
  • D. Only 2 is true

Answer: B

 

NEW QUESTION 69
How does the use of product descriptions support the 'focus on products' principle?

  • A. By documenting the costs for the product
  • B. By documenting the scope tolerance for the project
  • C. By documenting the quality expected by the customer
  • D. By documenting the delivery date for the product

Answer: C

Explanation:
Reference http://prince2.wiki/Focus_on_products

 

NEW QUESTION 70
Which theme defines the accountability for realization of the project's benefits?

  • A. Plans
  • B. Progress
  • C. Organization
  • D. Quality

Answer: C

 

NEW QUESTION 71
Which is a true statement about acceptance criteria?

  • A. Acceptance criteria are used to produce the customer's quality expectations
  • B. Acceptance criteria should be agreed between the customer and the supplier
  • C. Acceptance criteria are less specific and precise than customer's quality expectations
  • D. Once agreed, acceptance criteria CANNOT be changed

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 72
Which is a purpose of the Managing a Stage Boundary process?

  • A. Control the link between the Project Manager and the Team Manager(s)
  • B. Review and close any risks and issues identified during the previous stage
  • C. Approve the next Stage Plan
  • D. Provide the Project Board with sufficient information for approving the next stage

Answer: D

 

NEW QUESTION 73
......


How to book the PR2F Exam

These are following steps for registering the Exin PR2F exam. Step 1: Visit to Pearson VUE Exam Registration Step 2: Signup/Login to Pearson VUE account Step 3: Search for Exin PR2F Exam Certifications Exam Step 4: Select Date, time and confirm with payment method

 

Authentic Best resources for PR2F: https://www.actualtorrent.com/PR2F-questions-answers.html

PR2F Test Engine Practice Exam: https://drive.google.com/open?id=1IhmJDSzat42gBHG_-WGEDcSBpfBycpeZ