NEW QUESTION # 40
You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received.
Which planning strategy supports the consumption of planned independent requirements by dependent requirements for the semi-finished material?
- A. Planning with final assembly (40)
- B. Assembly processing with production orders (82)
- C. Planning at assembly level (70)
- D. Production by lot size (30)
Answer: C
NEW QUESTION # 41
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?
- A. When several production versions are maintained for one product
- B. When multiple planned orders are scheduled in parallel on one resource
- C. When alternative resources are used within one operation
- D. When several operations are maintained for one product
Answer: C
NEW QUESTION # 42
What is the purpose of the pull list in material staging?
- A. To control the flow of material from the supplier to the central storage location
- B. To control the flow of material from the production storage location to the central storage location
- C. To control the flow of material from the supplier to the production storage location
- D. To control the flow of material from the central storage location to the production storage location
Answer: D
NEW QUESTION # 43
For a production version to be valid and consistent, what requirements must be fulfilled? Note: There are 3 correct answers to this question.
- A. The lot size range must be within the lot size range of the assigned routing.
- B. The assigned routing and bill of material (BOM) must be valid in the entire validity period.
- C. The deletion flag must NOT be set for the bill of material (BOM) or the routing.
- D. The assigned routing and bill of material (BOM) must have the same validity period.
- E. The consistency check must be performed.
Answer: A,B,E
NEW QUESTION # 44
You want to verify that the properties of a component batch align with the required properties of the raw material intended for a specific process order. What function do you use to accomplish this?
- A. Batch where-used list
- B. Batch determination
- C. Batch information cockpit
- D. Batch number assignment
Answer: B
NEW QUESTION # 45
Your company manufactures materials whose characteristics differ for each manufacturing process.
Which application do you choose in SAP S/4HANA to track and use this information in all areas of logistics?
- A. Process order management
- B. Quality management
- C. Batch management
- D. Engineering change management
Answer: C
NEW QUESTION # 46
What is a prerequisite for the consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
- A. A sales order is delivered.
- B. MRP creates a planned order.
- C. MRP creates a dependent requirement.
- D. A sales order is created.
Answer: D
NEW QUESTION # 47
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.
- A. Automatic print on order creation
- B. Automatic goods receipt on confirmation
- C. Default order types
- D. Automatic goods issue on confirmation
- E. Automatic release on order creation
Answer: B,C,E
NEW QUESTION # 48
How are dependent requirements for assemblies created?
Note: There are 2 correct answers to this question.
- A. They are created on the assembly level during the planning run.
- B. They are created together with the independent requirement for the finished product.
- C. They are only created for multilevel bill of material (BOM) structures.
- D. They are created with exact times in Advanced Planning.
Answer: A,D
NEW QUESTION # 49
What data can you maintain in the items detail screen of a bill of material (BOM)?
Note: There are 2 correct answers to this question.
- A. Co-product
- B. Change number
- C. Alternative item group
- D. Lot size
Answer: A,C
NEW QUESTION # 50
Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.
- A. Material type
- B. Procurement type
- C. MRP group
- D. MRP type
Answer: B,D
NEW QUESTION # 51
How can you achieve a feasible production plan when there are capacity constraints?
Note: There are 3 correct answers to this question.
- A. Form optimum sequences to reduce setup times
- B. Execute an infinite production planning run for the critical resources
- C. Increase the capacity supply in a time-phased interval
- D. Determine a time period with available capacity on the planning board
- E. Reduce the planning time interval
Answer: A,C,D
NEW QUESTION # 52
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. Order (pool) chart
- B. Order (dispatched) chart
- C. Work center capacities chart
- D. Capacity requirements chart
Answer: C,D
NEW QUESTION # 53
In which master data objects do you maintain data to determine the duration of an operation for production?
Note: There are 2 correct answers to this question.
- A. Production version
- B. Work center
- C. Routing
- D. Material master
Answer: B,C
NEW QUESTION # 54
When working with the material status, for which business areas can you set a warning message?
Note: There are 2 correct answers to this question.
- A. Sales
- B. Purchasing
- C. Classification
- D. Plant Maintenance
Answer: A,D
NEW QUESTION # 55
What are some options for creating a production order?
Note: There are 2 correct answers to this question.
- A. By setting a Kanban container to empty
- B. By partially converting a planned order
- C. By converting a purchase requisition
- D. By setting a Kanban container to full
Answer: A,B
NEW QUESTION # 56
How can you set up a material as a phantom assembly?
Note: There are 2 correct answers to this question.
- A. Select a special procurement type inside the material master
- B. Select a special explosion type inside the material master
- C. Select a special procurement type inside the material BOM (bill of material)
- D. Select a special explosion type inside the material BOM (bill of material)
Answer: A,C
NEW QUESTION # 57
When do you use variant bills of material (BOMs)?
- A. When multiple materials have similar BOMS
- B. When multiple materials have multiple BOMS
- C. When a material has multiple BOMs
- D. When a material has a configurable BOM
Answer: A
NEW QUESTION # 58
What is the purpose of using a low level code?
Note: There are 2 correct answers to this question.
- A. To determine the priority of alternative components inside the material BOM (bill of material)
- B. To determine the lowest explosion level at which a material occurs in all the product structures
- C. To determine the sequence in which materials are planned in MRP
- D. To determine the use of subitems inside the material BOM (bill of material)
Answer: B,C
NEW QUESTION # 59
What are some advantages of using Kanban for material supply? Note: There are 2 correct answers to this question.
- A. Replenishment is always triggered on a regular basis.
- B. Replenishment is only triggered when components are required.
- C. Material stock is built up for a long period of time in production.
- D. Material is only kept available in small quantities in production.
Answer: B,D
NEW QUESTION # 60
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
- A. Order type
- B. Requirements profile
- C. Planning strategy
- D. Requirements type
Answer: C,D
NEW QUESTION # 61
......